2026-10-02 19:23 Last Updated At:10-04 15:43

Government reaches settlement arrangement with MTRCL on Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express Rail Link project and Shatin to Central Link project

The Government today (October 2) reached a settlement arrangement with the MTR Corporation Limited (MTRCL) on the Hong Kong Section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) project and the Shatin to Central Link (SCL) project.

MTR, Photo source: reference image

MTR, Photo source: reference image

The XRL and SCL are railway projects implemented by the MTRCL under entrustment from the Government. Following the dispute resolution approach specified under the entrustment agreements for the two projects, the Government and the MTRCL conducted multiple rounds of negotiations, and reached a settlement arrangement today. In relation to the programme delay in the construction of the XRL project, the MTRCL will pay HK$2.25 billion to the Government. On the other hand, in respect of disputes relating to the SCL project, the MTRCL has in the past proactively shouldered the additional project management cost (PMC) for the whole project and additional costs arising from the quality incident of the Hung Hom Station Extension (HUH Incident), totalling approximately HK$2.8 billion. Both parties have agreed not to pursue any claims against each other for the delay of the SCL project. The settlement arrangement has fully taken into account the responsibilities of the MTRCL on the programme delays of the two projects.

A spokesman for the Transport and Logistics Bureau said, "The Government has been following up in a serious, rigorous and professional manner with the MTRCL on its responsibilities as the project manager in respect of programme delays in the construction of the XRL and SCL projects, in order to safeguard the legitimate interests of the Government and the public. Under the mutually agreed dispute resolution approach, personnel from both the Government and the MTRCL organised and analysed a substantial volume of materials, and fully consulted independent and professional engineering and legal advice in the process to clarify the liability issues involved. The two sides engaged in multiple rounds of discussions, working proactively to resolve the disputes and successfully reaching a consensus in the end.

"Following the programme delays of the XRL and SCL projects, the Government and the MTRCL have thoroughly reflected on the experiences, and put in place a series of enhancements to strengthen the governance, monitoring and cost management mechanisms of railway projects over the past few years, with a view to further improving the oversight of project management and process at the institutional level. The Government and the MTRCL have also implemented the enhanced mechanisms in railway projects currently under way, including Kwu Tung Station, Tung Chung Line Extension, Oyster Bay Station, Tuen Mun South Extension, Hung Shui Kiu Station and the Northern Link Project. The Government will continue to closely monitor the progress and delivery performance of railway projects, and urge the MTRCL to implement new railway projects on schedule and within budget. At the same time, in accordance with the project agreements for the aforementioned new railway projects, the MTRCL is required to bear all construction and operational risks associated with the new railway projects, including the risk of project cost overruns," the spokesman added.

The Transport and Logistics Bureau, Photo source: reference image

The Transport and Logistics Bureau, Photo source: reference image

The XRL and the SCL are railways funded and owned by the Government, which has entrusted the MTRCL with the design, construction, testing and commissioning of the projects. Construction of the XRL commenced in 2010, and was originally scheduled for commissioning in August 2015. Due to programme delay and cost overruns, the Government and the MTRCL signed a definitive agreement in 2015, agreeing to extend the Programme to Complete to the third quarter of 2018, and increase the estimated Cost to Complete (CTC) by HK$19.42 billion from HK$65 billion to HK$84.42 billion, which is then capped at this level. In November 2015, prior to the Government's application to the Legislative Council (LegCo) for additional funding, the MTRCL announced the distribution of a special dividend to its shareholders. The Government, as the MTRCL's major shareholder, received a total amount of HK$19.51 billion in special dividend. The XRL formally commenced operation in September 2018.

High Speed Rail West Kowloon Station, Photo source: reference image

High Speed Rail West Kowloon Station, Photo source: reference image

Construction of the SCL commenced in 2012. The Tai Wai to HungHom Section (linking the MaOnShan Line and the West Rail Line to form the TuenMa Line) was originally scheduled for commissioning in December 2018, while the Cross-harbour Extension (extending from HungHom to the WanChai Exhibition Centre and Admiralty) was originally scheduled for commissioning in December2020. Due to a series of events, including the archaeological discoveries at Sung Wong Toi Station, wartime bombs uncovered at the Exhibition Centre Station site, unforeseen ground conditions, and the HUH Incident, the TuenMa Line was eventually fully commissioned in June2021, while the Cross-harbour Extension commenced operation in May2022. The estimated CTC also increased from HK$79.82billion to HK$90.73billion (the additional funding of HK$10.91billion sought from the LegCo at that time did not include the additional PMC for the whole project and additional costs arising from the HUH Incident totalling approximately HK$2.8 billion, which the MTRCL proactively shouldered).

Employers, contractors and employees should be aware of electrical safety at work during rainstorms

As the rainstorm warning has been issued by the Hong Kong Observatory, the Labour Department (LD) reminds employers and contractors that they should adopt necessary work arrangements and take suitable safety measures to protect the safety of their employees when they are carrying out electrical work or handling electrical plant.

A spokesman for the LD said today (October 4) that employers and contractors should avoid assigning employees to carry out electrical work (such as electric arc welding work) or handle electrical plant at places affected by rainstorms, and should refer to the "Code of Practice in Times of Adverse Weather and 'Extreme Conditions'" and the "Guide on Safety at Work in times of Inclement Weather" issued by the LD.

Even if electrical work is carried out or electrical plant is handled at places not affected by a rainstorm, suitable safety measures must still be adopted to prevent an electric shock as the air would be more humid. Such measures include:

(i) Ensure that all live parts of an electrical installation are isolated from the power supply source and rendered dead, and the isolation from the power supply source must be maintained as long as electrical work is being carried out;

(ii) Before carrying out any electrical work or handling any electrical plant, cut off and lock out the power supply source, then test the circuit concerned to confirm that it is dead and display suitable warning notices, and issue a work permit thereafter;

(iii) Ensure that protective devices (such as suitable and adequate fuses and circuit breakers) for the electrical installations or electrical plant have been installed and maintained in good working order, and portable electric tools must be double-insulated or properly earthed;

(iv) Provide suitable personal protective equipment such as insulating gloves and insulating mats for employees; and

(v) If live electrical work is unavoidable, a comprehensive risk assessment should be conducted by a competent person and the appropriate safety precautions should be taken to remove or properly control the electrical hazards involved before such work can proceed.

In addition, employees should co-operate with the employer or contractor to follow the safety instructions and use the safety equipment provided.

The LD has published guidebooks and leaflets on electrical work safety. These safety publications are available free from divisional offices of the department or can be downloaded from its website (www.labour.gov.hk/eng/public/content2_8.htm).

Should there be any questions about occupational safety and health matters, please contact the Occupational Safety Officer of the LD at 2559 2297.

Source: AI-found images

Source: AI-found images

Recommended Articles